What to check before you file in the City of Miami

The City of Miami takes building permit applications in one system and reviews drawings in another. Early delays often come from the handoff between the two.

Painted illustration: a set of floor plans beside a checklist with four boxes ticked and the last one still open

Two systems, one application

The City of Miami takes building permit applications in iBuild and reviews drawings in ProjectDox, its electronic plans review system. You apply in the first and upload in the second.

After you apply, the City sends an email with an Applicant Upload Task. You upload the drawings and documents in ProjectDox and then mark the task complete. The City states that the task must be completed for the review to begin. A set that is uploaded but not marked complete is not in review.

Prescreen comes before review

The City's guide says a permitting coordinator reviews the application and submittals for acceptance, and it calls this the prescreen phase. A package returned at prescreen is back on your desk, so the checks worth doing on your side are the ones a coordinator does: every required document is there, every sheet is named and signed the way the City asks, and the application matches the drawings.

More than one department reviews

The City's guide names Building, Resilience and Public Works, Planning and Zoning among the departments that review. Comments can arrive from more than one of them in a round. Decide before filing who on your team answers each department.

The City's guide gives an estimate of approximately 14 business days for building permit applications. It is the City's estimate for its review, not a time to permit, and the City can change it. Check the guide for the current figure.

A short list before you press submit

  • The owner, address and folio on the application match the drawings and the survey.
  • The scope of work on the application says the same thing as the cover sheet.
  • Every sheet in the index is in the set, and nothing in the set is missing from the index.
  • Drawings are signed and sealed by the design professionals of record in the format the City asks for.
  • You know which County reviews the scope needs, and who is filing them.
  • One person has the login, receives the task emails and is responsible for marking tasks complete.

Sources

Read on November 20, 2026. Agencies change their rules and systems; check the source before you act.

General information, not legal advice. The agency decides every permit. OwnRep Miami is a private firm and is not affiliated with any government agency.

More from the blog