How to answer a round of review comments
A comment round is a list of questions. Packages come back a second and third time when the answers are partial, late, or filed in a way the system does not read as an answer.

Read all of it before anyone draws
One round can hold comments from several departments. Put every comment in one list with four columns: the comment, the sheet, who answers it, and the date the answer is due. A comment with no owner is the one that comes back.
Answer the question that was asked
A reviewer needs to see where the answer is. Write a response to each comment that names the sheet and the detail that changed. If you disagree with a comment, say so in the response and give the code section or the reason. Silence reads as a missed comment.
A change made for one reviewer often touches another reviewer's sheets. Check the whole set for the same dimension, note or detail before you send it back.
File it the way the system expects
In the City of Miami, corrections arrive as a Resubmit Applicant Task. The City's instructions say to replace each sheet a reviewer marked, and to give the corrected page exactly the same name it had before. The City states that an application is not accepted if the naming convention is not followed.
As with the first upload, the task has to be marked complete. Until it is, the set is with you, not with the City.
Know which clock is running
Florida law sets time limits for local governments to act on building permit applications, counted in business days from a complete application, and gives the applicant a set number of business days to send revisions after a written notice. The limits depend on the type of project and the statute has changed more than once, so read the current text of section 553.792 for your case.
While comments sit unanswered, the time belongs to you. The fastest part of a permit to shorten is the part on your own desk.
When the same comment returns
- Ask the reviewer what they need to see, in writing, and keep the answer with the permit record.
- Check that the corrected sheet was uploaded under exactly its original file name.
- Check that the response letter points to the right sheet number after the set was re-indexed.
- If the comment needs a design change, take the cost and the delay to the owner the same day.
Sources
- City of Miami: Submit Plans (Drawings) & Documents Electronically
- City of Miami: Guide to Getting a Permit
- Florida Statutes, section 553.792: building permit application to local government
Read on November 20, 2026. Agencies change their rules and systems; check the source before you act.
General information, not legal advice. The agency decides every permit. OwnRep Miami is a private firm and is not affiliated with any government agency.