After the permit is issued: three things that stop a job
An issued permit can still expire, inspections can be held for a missing notice, and a finished building cannot be occupied until the permit is closed. Each one is avoidable.

1. The permit runs out
A permit that goes too long without a valid inspection can expire. Miami-Dade County's page on extensions and reissues says a permit extension gives an additional 180 days to obtain a valid inspection, and that revisions do not extend a permit.
That is the County's description of its own permits. Cities in Miami-Dade issue their own permits and publish their own procedures, so check the rule with the department that issued yours.
On a job that has paused for financing, a contractor change or a redesign, put the date of the last approved inspection in the weekly update. It is the date that matters.
2. No notice of commencement
Florida's construction lien law requires a notice of commencement to be recorded and posted on the site before the first inspection. A separate section says that, for contracts above the amount set in the statute, if a copy of the notice has not been filed with the permitting authority, the authority may not perform or approve later inspections until it is filed.
The owner signs the notice. For an owner who is abroad, signing and recording take time, so start when the permit is close to issue and not on the day the contractor calls for the first inspection. The statute has conditions and exceptions; read the current text or ask your attorney.
3. The permit is never closed
In the City of Miami, a certificate of occupancy is for new construction or a change of use, and a certificate of completion is for remodels, renovations and shell buildings. The City says it needs the permit to be final before it can issue either one: all outstanding permit revisions and requests completed, and all final inspections approved.
The City also offers a temporary certificate of occupancy for early occupancy of a project that is still under minor construction. It is valid for a limited period, and its inspections are separate from the final ones.
Open revisions are the usual surprise. A field change that was built but never filed as a revision will hold the certificate at the end. Keep a list of revisions from the first day of construction.
Sources
- Miami-Dade County: Other Permits (extensions and reissues)
- Florida Statutes, section 713.13: notice of commencement
- Florida Statutes, section 713.135: notice of commencement and building permits
- City of Miami: Get a Certificate of Occupancy (CO) or Completion (CC)
- City of Miami: Get a Temporary Certificate of Occupancy (TCO) or Completion (TCC)
Read on November 20, 2026. Agencies change their rules and systems; check the source before you act.